Commercial Building Permits

New Commercial Construction

New commercial construction in Banks County is a two-phase process. Phase I is the land disturbance and civil engineering phase. The County works hand-in-hand with the GSWCC (Georgia Soil and Water Conservation Commission) to make sure that project supervisors are implementing best practices for erosion control and protection of our soil and water resources. To apply for a Phase I permit, you will need to submit ESC plans to the Planning Office. The Planning Office will need the completed Phase I application packet and a digital copy of ESC plans as well as a civil site plan emailed to PlanningOffice@co.banks.ga.us. Our team will review your digital plans for local compliance before you print hard copies. Then we will submit your printed ESC plan to GSWCC for review.

If your project does not require an ESC plan, you should still submit a civil site plan. You must be cleared for Phase I before a Phase II permit will be issued.

Phase II covers the building construction aspect of the project. To apply for a Phase II permit, you will need to submit a completed Phase II application packet and a digital copy of your construction plans to PlanningOffice@co.banks.ga.us (you may submit fire suppression plans separately if needed.)

Pre-construction meetings will typically take place before issuance of Phase I and Phase II permits. No work shall take place until permits have been issued.

Note: We will not accept incomplete application packets to secure early reviews on construction plans. Please submit your entire packet to be considered for review.

 